Williamson Lane, from state grant to final payment
How two NJDOT Municipal Aid grants became a rebuilt Williamson Lane, from delays and a single bid in 2024 to final payment on July 20, 2026.
By Kevin French · · 3 min read
Road projects paid for with state grants take longer than most people expect. Williamson Lane is a good example of why, and of how one gets finished.
The project ran from state grant awards through delays, a single bid, a change order and three payments. The final check was approved on July 20, 2026. Here's the record.
The money
Williamson Lane was funded mostly through the New Jersey Department of Transportation's Municipal Aid program. The township's grant records show two awards. Fiscal year 2022 brought $240,000 for phase 1, and fiscal year 2023 brought $234,990 for phase 2.
That's $474,990 in state money for one road.
Why it took time
The FY2022 grant agreement required a construction contract by October 21, 2023. That didn't happen, and the reasons are laid out in Resolution 57-2024, adopted March 18, 2024.
The project needed a right-of-way acquisition on one lot to widen the pavement and shoulder. Then new home construction along the road meant utility companies, including South Jersey Gas, needed to dig in the right-of-way for new service connections. The gas work was done and the trench restored in 2024.
But when the township engineer inspected on March 12, 2024, a new home on the road still needed its electrical and communications services installed. Paving a new road and then letting utilities cut into it a few months later is a fine way to waste a grant.
So the township asked for more time. In September 2023 the township had requested an extension, and NJDOT approved six months, moving the deadline to April 22, 2024.
Resolution 57-2024 asked for three more months, to July 22, 2024. The engineer sent second notices to the utilities and asked public works to schedule routine stormwater maintenance and vegetation management along the full length of the road within sixty days.
July 1, 2024, the award
Bids were opened on June 26, 2024. The township received exactly one, from Asphalt Paving Systems, Inc.
The bid had two options, Base Bid No. 1 at $284,636.98 and Base Bid No. 2 at $542,135.98. The engineer and solicitor found the bid conformed to the specifications and to the Local Public Contracts Law.
On July 1, 2024, the committee adopted Resolution 115-2024, awarding the contract to Asphalt Paving Systems on Base Bid No. 2, covering phases 1 and 2, for $542,135.98. That was inside the July 22 date the township had requested.
At the August 19, 2024 meeting, the township administrator reported that the preconstruction meeting for Williamson Lane was set for that Wednesday.
November 4, 2024, the change order
On November 4, 2024, the committee adopted Resolution 174-2024, a change order of up to $108,427.19.
The change order added 2-inch milling and an asphalt overlay on High Street, from Tomlin Station Road to an existing pavement joint about 950 feet west. The public works superintendent and engineer found the contractor's proposal reasonable.
NJDOT confirmed that this kind of change order is allowed. The added items are treated as non-participating, so they have to be listed separately on the payment and state aid forms with the other location identified.
The resolution built in some room. If milling uncovered cracked or failing base under High Street, the contractor could repair it. And if the High Street work came in under the maximum, the public works superintendent could direct repairs on other township roads that needed attention for safety.
Every dollar of the change order remained subject to the chief financial officer certifying that funds were available.
The payments
On August 18, 2025, the committee approved Resolution 103-2025, Payment No. 2 to the contractor for $169,712.09, as recommended by the township engineer.
On July 20, 2026, I made the motion on Resolution 158-2026, approving Certificate and Payment No. 3, the final payment, for $13,002.67. The engineer recommended it in a letter dated July 8, 2026. The committee adopted it.
The same night, the committee approved Resolution 159-2026, accepting the contractor's maintenance guarantee for the Williamson Lane work. A maintenance guarantee gives the township protection if defects show up after the work is accepted.
What it shows
A state grant isn't money in the bank the day it's announced. It comes with deadlines, paperwork and outside parties like utility companies who work on their own schedules.
Williamson Lane needed two extension requests to get the timing right and avoid tearing up new pavement. It drew only one bid.
It picked up a change order that added a stretch of High Street to the same contract. And it closed with a final payment and a maintenance guarantee.
From the first grant to the final check, that's how a road gets done.