High Street priority pavement repairs, start to finish
How Harrison fixed High Street in stages since 2024, from a change order on another contract to a state grant and a 2026 change order.
By Kevin French · · 3 min read
Anyone who drives High Street near Tomlin Station Road knows the pavement. It's been on the township's list for years.
The fix has come in pieces. Here's how the record lays it out.
Fall 2024, a change order on another job
In 2024 the township already had a paving contractor under contract for Williamson Lane, Asphalt Paving Systems, at $542,135.98 for Phases 1 and 2.
On November 4, 2024, the committee approved Resolution 174-2024. It added a change order to that contract for 2-inch milling and a new hot mix asphalt surface along High Street, from the Tomlin Station Road intersection to an existing pavement joint about 950 feet west.
The ceiling was $108,427.19. The resolution explains why there was cushion built in. Once crews mill off the top layer, they sometimes find cracked base underneath that can't hold new asphalt. The money had to be there to fix it.
NJDOT signed off on the approach with one condition. High Street work had to be tracked separately from the state-funded Williamson Lane items on the payment forms. And if High Street came in under the cap, the Public Works superintendent could use the balance for other emergency and safety repairs on township roads.
The grant
Earlier, on June 17, 2024, the committee authorized an application to the Local Aid Infrastructure Fund (Res. 104-2024). It was written two ways. Phase 2 ran from Tomlin Station Road about 900 feet west.
Phase 3 ran from Tomlin Station Road about 3,000 feet east. If Phase 2 got funded elsewhere first, the township would go after Phase 3.
The award came through at $191,000.
On March 3, 2025, the township administrator reported the grant at roughly $190,000 against an engineer's construction estimate of about $175,000. The committee approved a $31,000 proposal from Remington & Vernick for final design, bidding support and construction inspection. The administrator noted most of that is chargeable to the grant.
Ordinance 19-2025 appropriated the $191,000. It went to public hearing on August 4, 2025. No residents spoke.
Bidding it twice
The first round brought one bid, $168,200, opened October 30, 2025. On December 1, 2025, the committee rejected it on the engineer's advice that the specifications needed substantial revisions (Res. 157-2025). State law allows that.
The project went back out. Bids opened April 15, 2026, and again one came in, from Asphalt Paving Systems at $172,200. On May 18, 2026, the committee awarded the contract at that price, contingent on NJDOT's concurrence (Res. 100-2026).
The 2026 change order
Once work started, the base under the road turned out worse than anyone could see from the surface.
On July 28, 2026, the township engineer issued an opinion letter. It said it would save time and money to extend the repairs about 600 feet onto the section of High Street east of Tomlin Station Road.
On August 3, 2026, the committee adopted Resolution 176-2026. Change Order No. 1 added $64,240. That brought the contract to $236,440, a 37.3 percent increase.
Anything over 20 percent triggers extra steps under the state's local contract rules. So the resolution spells out the findings. The conditions were unforeseen.
They showed up only after work began. Rebidding would interfere with finishing the job. And skipping the work would leave a safety hazard and more pavement failure on what the resolution calls an important collector road.
The resolution directs the clerk to publish a notice in the official newspaper with the added cost, the original price, the new total and the percentage. It goes on the township's report to the state Division of Local Government Services too. The chief financial officer certified the funds.
Paying more than the bid is never fun. But pavement that keeps failing costs more.
What's next
High Street isn't done. On June 15, 2026, the committee authorized a new Local Aid Infrastructure Fund application for Phase 3, from Tomlin Station Road to Main Street (Res. 137-2026).
If that one comes through, the record will say so here.