Election Day is Tuesday, November 3. Re-elect Kevin French in Column B. How to vote

The recordFrom the record

State grants Harrison has pursued and won since 2024

A plain accounting of the state grants Harrison Township applied for and won from 2024 to 2026, project by project, with the delays explained.

By Kevin French · · 3 min read

State grant money is the cheapest money a township can spend. Every dollar that comes from Trenton for a road or a park is a dollar that doesn't come out of a Harrison tax bill.

So here's the full list of what the record shows. Awards, amounts, and where each project stands. No rounding up.

The roads

Williamson Lane came in two pieces. NJDOT Municipal Aid paid $240,000 for Phase 1 (FY2022) and $234,990 for Phase 2 (FY2023).

Woodland Avenue drew $219,285 from the FY2024 Municipal Aid program. This one has waited on New Jersey American Water. The utility told the township on August 1, 2024 that it planned to upgrade its system inside the project limits, and Resolution 113-2025 records that the work hadn't started a year later. Paving a road right before a utility digs it up is how you waste a grant, so the township asked NJDOT for more time.

High Street Phase 2 won $191,000 from the FY2024 Local Aid Infrastructure Fund. The committee voted to apply on June 17, 2024 (Res. 104-2024), and Ordinance 19-2025 put the money on the books in August 2025.

A $100,000 Local Aid Infrastructure Fund grant covers priority beam guiderail installation.

Sherwin Road won $204,642 from FY2025 Municipal Aid for pavement and drainage work between Mullica Hill Road and Jackson Road. On June 17, 2024, I voted yes on the application (Res. 105-2024). The award came in 89 percent below the full estimated cost in the application, so the culvert replacement under the road was cut from the grant scope.

Public Works owns that culvert and has to replace it before the road is rebuilt. Resolution 209-2026, on the September 21, 2026 agenda, asks NJDOT to move the contract deadline from November 13, 2026 to May 13, 2027 for that reason.

Walking and biking

North Main Street pedestrian safety improvements won $175,000 from the FY2023 Safe Streets to Transit program. The sidewalks ran into Atlantic City Electric poles and guy wires, and the utility needed time to decide how to handle them. That meant several extensions.

All bids were rejected on December 1, 2025 (Res. 158-2025) so the specifications could be revised. On May 18, 2026, the committee awarded the contract to the low bidder at $168,325, pending NJDOT concurrence (Res. 99-2026).

Bridgeton Pike pedestrian improvements at Ella Harris Park won $68,000 from Safe Streets to Transit. That's a sidewalk between the park entrance and Mullica Hill Plaza.

The Mullica Hill Road Bikeway won $290,000 from the NJDOT FY2025 Bikeways program, per NJDOT's published recipient list. The application resolution (Res. 111-2024) describes a paved path separated from traffic on the south side of Mullica Hill Road, from Franklin Drive to Mullica Pond Park. Residents had voiced support for it.

County officials, who have jurisdiction over the road, said they would support a township project. On June 17, 2024, I voted yes on that application.

Parks

The Department of Community Affairs awarded $70,000 from its FY2024 Local Recreation Improvement program for Ella Harris Park Inclusive Playground Phase 2. The township asked for about $200,000 (Res. 68-2024) and took what the state offered.

The math

Ordinance 24-2024 appropriated $932,275 in one shot for six of these grants. Williamson Lane both phases, Woodland Avenue, the guiderail, Bridgeton Pike at Ella Harris Park and the recreation grant.

Add High Street, North Main Street, Sherwin Road and the bikeway, and the awards in this post total $1,792,917.

Still waiting

Not every application turns into a check. The record shows these as filed with no award yet.

David Drive and Station Court pavement and curb ramp work, filed with NJDOT's Local Transportation Projects Fund on June 17, 2024 (Res. 110-2024).

About $75,000 from DCA for Ella Harris Park accessibility improvements (Res. 54-2026, February 2, 2026). That one passed with my second.

High Street Phase 3, from Tomlin Station Road to Main Street, filed with the FY2026 Local Aid Infrastructure Fund (Res. 137-2026).

A New Jersey Historic Trust request to update the Mullica Hill Historic District survey, with an $18,906 township match committed if it's awarded (Res. 87-2026).

Why the delays matter

A grant has a clock on it. NJDOT expects a construction contract by a set date, and an extension has to be justified in writing. Most of the Harrison extensions that state a reason point to utility work, and one points to a grant that came in short.

That's worth watching. A grant you can't spend is worth exactly as much as a grant you never got.

The full ledger lives with the township's records, and every number above traces to a resolution, an ordinance or an NJDOT award list.

Keep reading

Experience matters. Your vote matters. Harrison matters.

Tuesday, November 3. Re-elect Kevin French. Column B.

Vote Tuesday, Nov 3Kevin French · Column BHow to vote