Willowbrook Farms resurfacing, from patching to microsurfacing
The $376,014.76 Willowbrook Farms road project under Res. 81-2025, how microsurfacing works, why it looked rough at first and how long it should last.
By Kevin French · · 3 min read
Willowbrook Farms is one of the older and larger developments in the township. By 2024 its streets showed it.
The fix took more than a year from first conversation to final coat. Here's how it went, from the minutes.
2024, figuring out the approach
The first mention came at the May 20, 2024 regular meeting. The township administrator reported he had met with a contractor at Willowbrook Farms to talk about paving the development's roads.
At the July 15, 2024 meeting, a committee member asked where things stood. The administrator said he would reach out to the contractor that had done the work in the High Pointe development and go over what could be done in Willowbrook.
He added a caution. If the township used the same method as High Pointe, Willowbrook residents would need to be told what was going to happen and what to expect afterward.
On August 5, 2024 he laid out the plan. The township would award a contract to microsurface the entire development under state contract.
Crack sealing had to happen first, and some milling and base repairs had to be done in advance. There would be a communication plan with the homeowners association.
By August 19 he had emailed Willowbrook residents. He explained that contractors wanted the township to do the upfront work of marking out and measuring the milling and paving before they would quote it.
June 2, 2025, the award
The contract came to the committee on June 2, 2025 as Resolution 81-2025.
It awarded the work to Asphalt Paving Systems of Hammonton for milling and resurfacing portions of the Willowbrook subdivision. The amount was $376,014.76, under New Jersey State Contract T2507.
Using a state contract matters. Under state law, a town can buy goods and services by resolution through contracts the state has already put in place, without advertising its own bid. The resolution notes the township needed this work on a timely basis.
The committee approved it.
Summer 2025, the prep work
At the June 16, 2025 meeting, the administrator reported the contractor was starting in Willowbrook that day.
He described the phases. The homeowners association president got an email to share with residents. Public works would handle crack sealing, sinkholes and inlet repairs.
The final phase, the microsurfacing of the whole development, was planned for late summer or early fall. He said the work should keep the roads in good shape for at least another 5 to 8 years.
By August 18, crews were patching sinkholes in Willowbrook to get ready for that final phase, which had to be done by the end of the year.
On September 15, the administrator gave a tentative start of October 3 for the topcoat, weather permitting. Crews were still patching, rebuilding boxes and crack sealing.
The association would be asked to tell residents to move cars and keep access open for school buses and trash trucks. He was honest that it would be disruptive and would take 5 to 7 days.
October 2025, the topcoat and the look
The final phase started the week before the October 20, 2025 meeting. Detailed notice went to the association, and the administrator said residents were helpful and cooperative.
Then he told the committee what everyone in Willowbrook could already see. The fresh surface was uneven and brown. Residents weren't happy with the look.
Here's why. Microsurfacing takes time to cure, possibly 6 to 9 months. It goes down better in cooler weather so it isn't sticky.
It costs about a quarter of what milling and paving costs. And it should buy roughly 5 to 8 years before a full mill and pave is needed.
He said Willowbrook was chosen ahead of others for its age and size, and that public works had done a lot of the prep.
So if your street looked like a chocolate bar that had been left in the car, that was the curing stage, not the finished product.
November 2025, done
At the November 3, 2025 work session, the mayor said he'd received a lot of positive feedback from Willowbrook. The streets were already starting to look good.
On November 17, 2025, the administrator reported that the township had just finished the Willowbrook project.
What residents should take from it
Microsurfacing isn't a full repave. It's a new surface laid over roads that have been patched and sealed first.
It looks rough before it cures. And it costs a fraction of milling and paving, which lets the township stretch road dollars across more neighborhoods.
At the same November 3 meeting, a resident from another development asked about his roads. The administrator said that development would be one of the next in line for microsurfacing.
Willowbrook was the big test. It's the model for the developments that come next.