The Swamp Road washout of March 2024 and the response
In March 2024 floodwater wiped out part of Swamp Road. How the county, utilities and township restored three homes within a day and planned the fix.
By Kevin French · · 3 min read
In March 2024, a few days before the committee's March 18 meeting, part of Swamp Road was simply gone.
By the March 18, 2024 meeting, the committee had a full account. This post pulls together what the minutes recorded that night and in the months after.
What happened
The road dated back roughly 80 to 85 years. It started as a private road built on an old railroad bed, a spur off the main line to a lumberyard. The township later took ownership of a portion of it, including the stretch that failed.
It was built the way roads were built then. Small 24-inch pipes ran under it to carry water from one side to the other.
The account given at that meeting described what went wrong. With the water table historically high, a large basin had formed behind the road. County OEM used a drone to map its edges and depth, and its estimate was more than 500 million gallons of water. Back in the woods, about half a mile in, the water had risen six to ten feet up the trees.
When it let go, it went through in minutes. The road was washed out, and a wide new ravine replaced what had been a stream bed. Uprooted trees 50 to 60 feet long lay across it.
The first 12 hours
Three homes in the Swamp Road area took the worst of it. Power lines and water lines serving them were torn out.
The county ran the command post and coordinated with state agencies. Police and fire were on scene. The response pulled in New Jersey American Water and Atlantic City Electric directly.
Early on, the families were told there was a better than even chance they'd have to evacuate for at least a night or two. They didn't. Within eight to ten hours electricity was back, and temporary water lines were in place.
All three homes had power and water in under 12 hours. Generators kept their refrigerators and freezers running in between.
The committee put its thanks to the Public Works crew and the responders on the record that night.
At the April 1, 2024 work session, a Swamp Road resident thanked the township and the emergency responders and said they were grateful the necessities were restored by evening.
Cleanup and the creek
The torrent carried debris across Mill Road into Raccoon Creek on the west side of Main Street. Glass bottles, trash and old car parts, possibly fill from when the road was built generations ago. A resident reported it to the township, and the concern became what was now sitting in the creek.
NJDEP's interest was twofold. How any road restoration would change flow downstream, and how much of the blown-out area should be cleaned out versus left alone.
The plan that followed
On April 1, 2024, the administrator reported a pre-application request had gone to DEP to review options for Swamp Road. Recent rainstorms hadn't changed anything at the site.
The temporary water line was the clock. It needed to be replaced before cold weather, no later than October. The township engineer and administrator discussed connecting to New Jersey American Water's main, since the old line had been private, and doing the work under DEP's permit-by-rule conditions.
On April 15, 2024, the administrator reported continued contact with DEP. He expected the water line work to finish sooner than October, and the township was looking at an alternate route for emergency access.
On May 20, 2024, the goal was set. Start the secondary road and the water line after Harrison Township Day.
On July 15, 2024, the administrator reported crews might begin clearing for the access road at Swamp Road, weather permitting, and the township was moving to replace the permanent water line. The contractor said service interruptions for residents should be short.
What it showed
Every resident on a back road wonders what happens if the road between them and everything else disappears. In March 2024, three Harrison households found out.
The answer, from the record, is that a county emergency plan kicked in fast, two utilities got around the normal process in hours, and the township followed with a methodical plan for the long fix.
The lesson in the minutes is that the water table is historically high now, and a road built with 24-inch pipes 85 years ago wasn't built for it. Infrastructure from that era has to be watched.