Performance and maintenance bonds, explained with Harrison examples
Why Harrison holds a developer's money until the roads and pipes are right, using Brookside Reserve and Remington Estates as examples.
By Kevin French · · 3 min read
A lot of township agendas carry resolutions with titles a mile long about performance guarantees and maintenance guarantees. They look like boilerplate. They're one of the better protections residents have.
Here's what they do, using two Harrison developments as examples.
The basic idea
When a builder gets approval for a subdivision, the plans include public improvements. Streets, curbs, stormwater systems, sewer lines, planted buffers. Things the township may own and maintain someday.
Before that work is finished, the builder posts a performance guarantee. It's usually a surety bond or a bank letter of credit, plus a cash piece, often 10 percent. If the builder walks away, the township can use that money to finish the job instead of leaving residents with half a road.
As work gets done, the township engineer inspects it and the builder can ask for a reduction. When everything passes, the performance guarantee is released and a smaller maintenance guarantee takes its place, typically for two years. If something fails in that window, there's money to fix it.
The committee votes on each step. That's why these show up so often.
Brookside Reserve
Bruce Paparone's Brookside Reserve, on what was Block 29, Lot 10, is a good walk through the whole cycle.
For Section 2, the developer posted a TD Bank letter of credit for $638,228.70, dated March 4, 2024, plus $83,000 in cash. The committee approved the form on March 18, 2024 (Res. 53-2024). The engineer's estimate for the 10 percent cash piece was $70,914.30, so the overpayment went back to the developer (Res. 103-2024, June 17, 2024).
On August 5, 2024, I made the motion to approve the first reduction for Section 2 (Res. 128-2024). The engineer's July 31, 2024 report backed it. The surety dropped by $402,939.55 and the cash bond by $44,771.06, leaving $261,432.39 posted.
Work completed, money released. Work not completed, money held.
Section 1 shows the other side. The developer asked for a full release and the committee said no twice. On October 20, 2025 (Res. 125-2025), the engineer's October 3 letter listed punch list items still open. On April 6, 2026 (Res. 73-2026), a March 6 letter did the same.
The third time, it was right. On July 20, 2026, I made the motion to release the Section 1 performance guarantee, a $548,185.21 letter of credit from 2022 (Res. 160-2026). In its place the developer owes a $76,136.84 maintenance guarantee and a $4,509 stormwater maintenance guarantee for two years. The resolution holds the release until the maintenance guarantee is posted and any outstanding inspection fees are paid.
On the October 5, 2026 agenda, Resolution 223-2026 would do the same for the Section 2 public facilities, replacing the $638,228.70 letter of credit with a $103,411.17 maintenance guarantee and a $15,502.50 stormwater maintenance guarantee.
Remington Estates
Russo Homes' Remington Estates subdivision, formerly Block 65, Lot 24.04, goes back further. The performance bonds date to November 10, 2015.
On November 4, 2024, the committee cleaned up the paperwork. A 2023 resolution had labeled the wastewater bond as site improvements. Resolution 170-2024 corrected it to identify the $525,547.44 bond as covering the wastewater system facilities. Resolution 171-2024, on the same agenda, released the $514,188.90 site improvements bond after the engineer's November 30, 2023 inspection report recommended release.
Then came the maintenance side. Russo had a $72,992.70 maintenance bond on the wastewater system, posted August 7, 2023. On November 3, 2025, the committee denied the request to release it (Res. 141-2025), citing an October 31, 2025 punch list from the engineer.
On December 15, 2025, after the engineer's December 5 report recommended release, the committee approved it (Res. 166-2025). Even then the bond couldn't go back until outstanding inspection and escrow fees were paid.
Why the township holds the money
The answer is simple. Once a bond is released, the pressure is gone.
A developer with $500,000 tied up in a letter of credit has every reason to fix a sunken inlet or a cracked curb. A developer who already has the money back has a lot less. The denials above aren't punishment. They're the system doing its job, and in both cases the release followed once the work matched the plans.
Residents rarely see this part. But the streets in a new neighborhood become everyone's streets eventually, and the bond is what keeps them from becoming everyone's bill.