Building permits and fees in Harrison, a plain guide
How construction permits work in Harrison, what the 2025 subcode fees are for common projects, and the fee relief available to veterans and nonprofits.
By Kevin French · · 4 min read
Finishing a basement, building a deck, swapping a water heater. Most of it needs a permit, and the fee is set by ordinance. Here's how the process runs in Harrison and what it costs.
Zoning first, then construction
The Construction Department's page lays out the order. Projects that change a building's footprint, lot coverage or use of space may need zoning approval first. Additions, decks, porches and new accessory structures start with a zoning application.
A construction permit can cover the building, electrical, fire and plumbing subcodes. Applications need original signatures, one per permit, and the township takes them by hand delivery or mail. Plans may be required for decks, pools, renovations, additions and new structures, though the Construction Official can waive drawings for minor work. An approved application is good for six months.
And no work starts until the fee is paid and the permit is in your hand.
You schedule your own inspections, through the township's online portal or by email to the Construction Office. The page is clear that an inspection isn't scheduled until you get a confirmation with a date. A final inspection comes before a certificate of occupancy or approval.
The township advises getting that final inspection before you make your last payment to a contractor. That's good advice anywhere.
The fee schedule
The committee updated the subcode fees in Chapter 97 with Ord. 07-2025, adopted March 3, 2025. When it was introduced, the township administrator said the goal was to bring Harrison in line with area towns and state-recommended fees.
A construction permit fee is the sum of the subcode fees. Here are the ones residents run into most.
New construction and additions are $0.038 per cubic foot, with a $200 minimum. Sheds over 200 square feet, uninsulated residential garages and similar small uninsulated accessory structures carry a $95 minimum instead. Renovations, alterations and repairs run $34 per $1,000 of estimated cost, with a $90 minimum.
Plumbing has a $90 minimum per application. Each fixture, like a toilet, sink, tub, dishwasher or water heater, adds $15. Sewer and water connections are $91 each.
On the mechanical side, for residential use groups, replacing a fuel-fired appliance is $60 for the first device and $30 for each additional one. A complete new or replacement HVAC system is a flat $120. A new fuel-fired generator is $100.
An aboveground pool is $100 if it's over 550 square feet and $75 if it's smaller. An in-ground pool is $300 over 550 square feet and $200 otherwise. A fireplace is $75, and so is a woodburning stove or chimney flue liner.
Demolishing a one- or two-family house is $100. A shed or garage is $75. For solar, the building fee is a flat $200, and the electrical fee starts at $200 for systems under 10 kilowatts.
Plan review for new construction, additions and major alterations is 20 percent of the construction permit amount, credited toward the permit fee. A certificate of occupancy for a new building is 5 percent of total fees, with a $25 minimum. Reinstating a lapsed permit costs 20 percent of the original permit or $25, whichever is greater.
The state adds its own training surcharge on top. The township collects it and sends it to the Department of Community Affairs.
For veterans and nonprofits
Two provisions help veterans.
The first is in Ord. 07-2025. For residential property owned by an American veteran, plan review for new residential construction, additions and major alterations is 5 percent of the permit amount instead of 20. Bring proof of veteran status when you apply.
The second came earlier, in Ord. 01-2025, adopted January 21, 2025. It created a fee waiver for veterans and for charitable, philanthropic, fraternal or religious nonprofits with federal tax-exempt status. The Township Committee can waive 50 percent of application fees, construction fees and surcharges. I seconded the motion to adopt it.
To ask for the waiver, write to the Municipal Clerk. A veteran includes a DD-214, DD-256 or similar discharge papers. A nonprofit includes its current federal tax-exemption certificate.
Either way, you need verification from the Tax Collector that taxes and assessments on the property are current. The clerk sends the request to the committee. Each project needs its own request.
Online permits
In October 2025 the committee took up Ord. 26-2025, tied to the state's electronic permitting system. It adds a surcharge of $1 per $1,000 of construction value, with a $5 minimum, on permits issued through that system. Demolition permits and asbestos or lead abatement permits are among the exemptions. The township solicitor explained that the state system requires the ordinance before the township can accept those payments.
Who to call
The Construction Department is in the Municipal Building at 114 Bridgeton Pike, open 8 a.m. to 4 p.m. on weekdays. Call 856-478-4111 or email construction@harrisontwp.us.
Ask before you build. A permit question is a five-minute phone call. A stop-work order is a much longer conversation.