July 21, 2025 regular meeting · A church sewer hookup and an early budget flag
True North Church gets its sewer approval, the tax lien sale gets explained, and the administrator flags early spending and health costs.
By Kevin French · · 2 min read
All five committee members were at the table for the July 21 regular meeting. The agenda mixed routine approvals with an early look at the budget.
True North Church connects to sewer
I made the motion on Resolution 91-2025, which approved a Treatment Works Approval application for True North Church. The church owns 333 and 351 Aura Road and is building a church and wellness center there.
A resident asked what a TWA actually is. The mayor explained it's the requirement that lets the church connect to the back end of Inspira's sewer. He added that the project puts no financial burden on the township. The resolution passed unanimously.
Tax lien sales, explained
The same resident asked about Resolution 90-2025, which authorized an electronic tax lien sale. The township solicitor explained that properties headed to a lien sale are typically four quarters behind. The township is selling the lien, not foreclosing, and the owner always has the chance to pay before the lienholder. That's worth knowing if you ever get one of those letters.
Roads and sidewalks
The committee introduced Ordinance 19-2025, appropriating $191,000 in NJDOT grant money for High Street Phase 2 pavement repairs. The township engineer reported the survey work was done for a sidewalk connection at Ella Harris Park, and the beam guiderail project was moving.
An early budget flag
The administrator reported that as of July 1, 53% of the budget was already spent. In past years the figure at that point ran 46 to 47%. He planned to have department heads review their lines and pinpoint the overage by the next meeting.
And the state actuary was recommending a 36% increase in health benefit costs. The township was looking at options.
Trash carts and the plant
The administrator was placing an order for 100 new trash carts. The vendor was sending a 64-gallon cart to test in a few tight spots around town. Same cart footprint, different shape, as he put it.
At the wastewater plant, the superintendent said surveyors had taken measurements, and the TWA submission looked like mid-August. That starts the process of putting the plant back in compliance with the state, with a possible bid by the end of the year.
The mayor commended the police department for its continued enforcement on Clems Run. And the administrator noted the township's IT contract with Kingsway comes up for renewal at the end of the year, saying the township has been very pleased with their work.